Home Latest PDF of PMI-SP: PMI Scheduling Professional

PMI Scheduling Professional Practice Test

PMI-SP exam Format | Course Contents | Course Outline | exam Syllabus | exam Objectives

The Project Management Institute (PMI) ® offers a professional credential for project schedulers, known as the PMI Scheduling Professional (PMI-SP)®. PMIs professional credentialing examination development processes stand apart from other project management certification examination development practices. PMI aligns its process with certification industry best practices, such as those found in the Standards for Educational and Psychological Testing.

Although many of the domains, tasks, knowledge, and skills outlined by the PMI-SP Examination Content Outline are also covered by the Practice Standard for Scheduling and PMBOK® Guide, there are some that are unique to the PMI-SP Examination Content Outline. Candidates studying for the examination will certainly want to include the current edition of the Practice Standard for Scheduling and PMBOK® Guide as two of their references, and would be well advised to read other current titles on project scheduling.

Schedule Strategy 14%
Schedule Planning and Development 31%
Schedule Monitoring and Controlling 35%
Schedule Closeout 6%
Stakeholder Communications Management 14%
Total 100%

Domain 1: Schedule Strategy (14% of examination)
Task 1 Establish project schedule configuration management policies and
procedures incorporating best practices, regulations, governing standards
and organization policies, and procedures to ensure accessibility, storage,
retrieval, maintenance, change control, and baseline schedule control.
Task 2 Develop schedule approach, based on the unique characteristics of the
project, including enterprise environmental factors and organizational
process assets, in order to define schedule requirements.
Task 3 Establish scheduling policies and procedures regarding methodology,
selection of a scheduling tool, scheduling parameters, performance
thresholds, activity granularity, presentation format, earned value
management (EVM) implementation, analysis techniques, and approval
requirements by using resources such as organizational process assets and
project documents in order to develop the schedule management plan and
standardize operational procedures.
Task 4 Develop the scheduling-related components for project management plans
(for example, integration, scope, cost, quality, resources, communication,
risk, and procurement management), through review of contract
requirements, in order to integrate scheduling activities into the overall
project management process.
Task 5 Provide information about project scheduling objectives and goals, the role of
the scheduler, and scheduling procedures to project team members to
facilitate effective participation in the project.
Knowledge and Skills:
 Applicable contract requirements, regulations, and governing standards
 Schedule control processes (for example, baseline control, status update procedure, variance thresholds)
 Scheduling development concepts (for examples, coding, work breakdown structures, organizational breakdown structure, resource breakdown structures)
 Project charter

Domain 2: Schedule Planning and Development (31% of examination)
Task 1 Develop the work breakdown structure (WBS), organizational breakdown
structure (OBS), control accounts (CA), and work packages through
communication with subject matter experts and stakeholders and analysis of
the contractual commitments in order to ensure completion of the project
scope.
Task 2 Define activities and milestones through communication with subject matter
experts, decomposition, and application of scheduling policies and
procedures to identify and document the work to be performed.
Task 3 Estimate activity durations, utilizing subject matter experts and scheduling
techniques such as three-point estimate, parametric, analogous and/or
Program Evaluation and Review Technique (PERT) in order to develop an
overall schedule model.
Task 4 Sequence activities, incorporating defined dependencies (internal, external,
and cross programs) milestones, and constraints (for example, calendars,
geography, contracts), in order to develop a logical, dynamic schedule model.
Task 5 Identify critical and near-critical path(s) using techniques such as Critical
Path Method, Critical Chain, Program Evaluation and Review Technique
(PERT), and Monte Carlo simulation in order to meet project delivery date
requirements.
Task 6 Develop the project resource breakdown structure (RBS), determine resource
availability, and assign resources to activities by working with functional
managers, project managers, and project team members in order to define the
resource constrained schedule.
Task 7 Adjust schedule model based upon resource availability, available budget,
and other known constraints in order to calculate the resource constrained
schedule.
Task 8 Align schedule with the overall program plan or integrated master plan (IMP),
through review of enterprise objectives and contract documentation, in order
to ensure accomplishment of overall program objectives.
Task 9 Analyze major milestones against statement of work (SOW), the contract,
and/or memorandum of understanding, to assess whether schedule model
delivery estimates meet required deadlines.
Task 10 Perform schedule risk analysis using quantitative tools or techniques (for
example, what-if scenarios, Monte Carlo simulation) in order to determine if
project milestone dates are achievable within acceptable risk tolerances.
Task 11 Obtain a consensus of the project customer, sponsor, project manager, and
project team members, in order to establish an approved baseline schedule.
Task 12 Establish the Performance Measurement Baseline (PMB), using organizational
processes and standard techniques, in order to enable performance measurement and management.
Knowledge and Skills:
 Scope statements, including deliverables and deadlines
 Work breakdown structure (WBS)
 Organizational breakdown structure (OBS)
 Resource breakdown structure (RBS)
 Cost structure as related to schedule development
 Activity definition
 Activity execution techniques (duration/time, effort/work)
 Dependency relationship types (Finish to Start, Start to Finish, Finish to Finish, Start to Start)
 Leads and lags
 Prioritization within the schedule model
 Resource groups
 Resource calendars
 Resource allocation techniques
 Activity Network Diagram (AND)
 Precedence Diagramming Method (PDM)
 Capacity requirements/resource requirements
 Contingency reserve or buffer (funds, budget, or time)
 Cost and schedule integration
 Schedule baselining
 Performance Measurement Baseline (PMB)
 Inter-project Dependencies
 Milestone definition
 Schedule model components
 Schedule risk-assessment techniques (for example, Monte Carlo simulation, PERT)

Domain 3: Schedule Monitoring and Controlling (35% of examination)
Task 1 Collect activity status at defined intervals from activity owners via reports,
meetings, inspections, or other standard procedures in order to update and
review the project progress.
Task 2 Collect resource information and updates via reports, timesheets, meetings,
inspections, or other standard procedures in order to report on resource
utilization and availability.
Task 3 Perform schedule analysis and audit, on in-house and subcontractor
schedules, using industry standards, guidelines and best practices in order to
identify and report project schedule, status, changes, impacts or issues.
Task 4 Identify alternative project execution options, using tools and techniques
such as what-if scenario analyses, in order to optimize the schedule.
Task 5 Incorporate approved risk mitigation activities into the schedule, by utilizing
defined change control processes, in order to establish a new performance
measurement baseline (PMB).
Task 6 Update the schedule model and document schedule baseline changes,
received through formal change-control processes, in order to maintain an
accurate schedule and facilitate forensic schedule analysis, if required.
Knowledge and Skills:
 Progress measurement techniques (for example, percent complete, actual/remaining duration, estimate to complete)
 Industry standards, guidelines, and best practices with respect to activity status update frequency, format, and content
 Metrics to monitor, analyze, and control the schedule
 Cost and schedule reserve analysis
 Activity prioritization
 Available data, logical data organization/relationships within data elements
 Electronic file storage and retrieval standards
 Resource breakdown structure (RBS)
 Resource calendars
 Resource groups
Resource allocation techniques
 Schedule risk analysis
 Project schedule change control
 Reserve analysis
 Knowledge of ongoing audit analysis
 Activity Network Diagram (AND)
 Precedence Diagramming Method (PDM)
 Schedule risk assessment techniques (for example, Monte Carlo simulation, Program and Evaluation Review Technique [PERT])
Schedule and cost variance management

Domain 4: Schedule Closeout (6% of examination)
Task 1 Obtain final acceptance of the contractual schedule components, by working
with sponsor and/or customer, in order to facilitate project closeout.
Task 2 Evaluate final schedule performance against baseline schedule, scheduling
approach and the implementation, using standard scheduling tools and
techniques, including solicitation of feedback from stakeholders, in order to
identify lessons learned and develop best practices.
Task 3 Update the organizational process assets, through documentation of
identified lessons learned and best practices, in order to Improve business
processes.
Task 4 Distribute final schedule reports, including earned value management (EVM)
calculations and variance analysis, to stakeholders in order to facilitate
project closeout.
Task 5 Archive schedule files (for example, final schedule model, schedule
management plan, periodic status reports, schedule change log), as per
defined procedures in order to satisfy contractual requirements and prepare
for potential forensic schedule analysis.
Knowledge and Skills:
 Contractual schedule components
 Schedule close-out procedures
 Feedback techniques
 Schedule review techniques
 Schedule issue management
 Transition planning

Domain 5: Stakeholder Communications Management (14% of examination)
Task 1 Develop and foster relationships with project stakeholders, consistent with
the communication management plan, in order to enhance support for the
project schedule.
Task 2 Generate and maintain visibility of project schedule, by working with the
project manager and/or stakeholders, in order to maintain stakeholder
support.
Task 3 Provide senior management and other stakeholders with verbal and written
schedule status updates and impact on schedule of corrective actions, as
defined by the communication management plan, in order to maintain
stakeholder awareness.
Task 4 Communicate schedule issues that could impact delivery of project scope or
adherence to the schedule management plan, in order to elevate awareness to
relevant stakeholders.
Knowledge and Skills:
 Targeting communications to senior management
 Methods and techniques used to maintain visibility of project schedule Elements of the communication management plan Oral and written communication tools and techniques
 Targeting communications to intended audience
 Presentation tools and techniques
 Negotiation
 Facilitation
 Cultural sensitivity and diversity
 Conflict resolution
 Project life cycle
 Stakeholder-impact analysis
 Change management/control
 Scheduling terminology
 Organizational process assets
 Project management software
 Project management information systems
 Schedule documentation and reporting techniques
 Scheduling data management procedures (for example, archiving, storage, retrieval)
 Estimation techniques (for example, analogy based estimation, parametric estimation, historical data, expert estimation)
 Scheduling methods (for example, critical path method, critical chain, linear, agile)
 Scheduling techniques (for example, resource leveling, schedule compression, simulation)
 Earned Value Management (EVM)
 Gantt Charts
 Quantitative and qualitative schedule analysis (for example, schedule performance index, baseline execution index, float analysis)
 Problem-solving tools and techniques
 Contract schedule requirements

100% Money Back Pass Guarantee

PMI-SP PDF trial Questions

PMI-SP trial Questions

PMI-SP Dumps
PMI-SP Braindumps PMI-SP braindump questions PMI-SP Practice Test
PMI-SP real Questions
PMI
PMI-SP
PMI Scheduling Professional
https://killexams.com/pass4sure/exam-detail/PMI-SP
QUESTION: 311
A company hires a scheduler for one of its projects. What skills should he possess to efficiently work with the project team? Each correct answer represents a complete solution. Choose three.
1. Performance control
2. Execution scheduling
3. Leadership
4. Feasibility planning
Answer: D, B, A
Explanation:
A scheduler schedules the constraints for the project into phases with respect to the time and resources available. He can be hired from outside a company, or from within a company. The basic roles of a scheduler are as follows: Feasibility Planning: A scheduler is the time management expert who paints a picture of the project. He develops a strategy for delivery and to gain consensus. Execution Schedule: A scheduler works with the project team to optimize and refine the schedule until an agreed schedule has been developed. Performance Control: A schedule is maintained by the scheduler who optimizes outcomes and instructs the project team on their presentation. It is important that the scheduler be aware of the changes and trends related to the project delivery. Answer option C is incorrect. This is the skill possessed by the project manager.
QUESTION: 312
Which of the following is NOT an output of the control schedule process?
1. Organizational process assets
2. Change requests
3. Project termination request
4. Project document updates
Answer: C
Explanation:
The project termination request is not an output of the control schedule. Early termination of a project is a closing process and usually does not stem from the project manager. The outputs of the control schedule process are as follows: Work Performance Measurements: The work packages and control accounts are documented and communicated to the stakeholders. Organizational Process Assets Updates: The assets that are updated are: corrective actions chosen and the reasons, causes of variance, and other types of lessons learned from project schedule control. Change Requests: It is processed for reviews and disposition through the
Perform Integrated Change Control process. Project Management Plan Updates: The elements that need to be updated are: schedule baseline, schedule management plan, cost baseline. Project Document Updates: The elements that need to be updated in project document updates are: schedule data and project schedule.
QUESTION: 313
You are the project manager of the NHQ project. This project is scheduled to last for six months and will require $345,000 to complete. If the project completes earlier than scheduled, your organization will receive a bonus of $5,000 per day for the early completion. Management has asked you to develop an aggressive schedule to realize as much of the bonus as possible, but you must be careful not to increase project risk beyond an acceptable level of risk exposure. Which of the following approaches is most likely to increase project risk?
1. Using the critical chain method
2. Crashing
3. Adding leads to the project work
4. Fast tracking
Answer: D
Explanation:
Fast tracking allows entire phases of the project to overlap and this action does increase risks. This is an approach that you would want to avoid in your project. Answer option B is incorrect.
Crashing adds labor to the project and typically drives project costs. Answer option A is
incorrect. The critical chain method considers the availability of project resources as part of its network diagramming technique. Answer option C is incorrect. Lead time allows project activities to overlap and may introduce project risks, but not to the extent of using fast tracking.
QUESTION: 314
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend
$2,073,654. What is this project's planned value?
A. $2,025,000
B. There is not enough information to know C. $4,500,000
D. $2,250,000
Answer: D
Explanation:
The planned value is the worth of the project if it were on time. In this instance, the project should be 50 percent complete, so the planned value is half of the project budget - $2,250,000. Planned value (PV) is the authorized budget assigned to the schedule work to be accomplished for a schedule activity or work breakdown structure component. It serves as a baseline against which real performance is measured. The theory of planned value is of vital importance to the project management team and it is important to keep careful track of this. The term planned value can also be in some situations referred to by the project management team and the project management team leader as the budgeted cost of work scheduled (BCWS). Answer option C is incorrect. This is the budget at completion. Answer option A is incorrect. This is the earned value for the project. Answer option B is incorrect. There is enough information to know.
QUESTION: 315
You are the project manager for your organization. You want to record some details about the work that the project team has to complete. You want to document the level of effort, where the work is to be performed, and the person who will be responsible for completing the work. Which of the following is the best place to document this information?
1. Activity attributes
2. Project management plan
3. Schedule Management Plan
4. Roles and Responsibilities Matrix
Answer: A
Explanation:
The activity attributes initially include the Activity ID, WBS ID, and the Activity Name, but it can evolve over time to include other components about the work. Activity attributes are an output of the Define Activity process. These attributes refer to the multiple components that frame up an activity. The components for each activity during the early stages of the project are the Activity ID, WBS ID, and Activity name. At the later stages, the activity attributes include Activity codes, Predecessor activity, activity description, logical relationship, successor activity, leads and lags, imposed dates, and constraints and assumptions. Activity attributes are used for schedule development and for ordering, selecting, and sorting the planned schedule activities in a number of ways within reports. Answer option B is incorrect. A project management plan is a formal document that defines how the project is being monitored, controlled, and executed. It is not the best answer. Answer option D is
incorrect. The roles and responsibilities matrix records the work and the person to record the work, but does not offer additional information such as locale for the work, level of effort, and other information. Answer option C is incorrect. The Schedule Management Plan defines how the schedule will be created, executed, and controlled.
QUESTION: 316
Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?
1. Communications management plan
2. Issues log
3. Project schedule
4. Schedule management plan
Answer: A
Explanation:
The communications management plan defines who needs what information, when the information is needed, and the modality the information is expected in. Answer option C is incorrect. The project schedule could include project management activities such as schedule communication, but the communications management plan is the best answer as this information is absolutely documented in this plan. Answer option D is incorrect. The schedule management is not the best location for this information. Answer option B is incorrect. The request for customer communication is not an issue, so this choice is not the most appropriate.
QUESTION: 317
Jenny is the project manager for her organization. Her project is not doing well on project schedule performance, and management wants her to predict how the project schedule and cost will end. Management has asked Jenny to report and forecast her project's performance based on the Judgmental methods. Which of the following judgmental methods will Jenny use to accomplish the task? Each correct answer represents a complete solution. Choose all that apply.
1. Forecast by analogy
2. Technology forecasting
3. Autoregressive moving average
4. Scenario building
Answer: D, B, A
Explanation:
The judgmental forecasting method incorporates intuitive judgments, opinions and subjective probability estimates. Some examples of judgmental forecasting are as follows: Composite forecasts Surveys Delphi method Scenario building Technology forecasting Forecast by analogy
Answer option C is incorrect. Autoregressive moving average is an example of the causal/econometric method.
QUESTION: 318
You work as a project manager for BlueWell Inc. You are creating the activity list for the project. The activity list is based on the work packages defined in the project's WBS. Activities provide a basis for all of the following information except for which one?
1. Scope baseline
2. Executing
3. Scheduling
4. Estimates
Answer: A
Explanation:
The project's scope baseline is not derived or provided by the project's activity list. The scope baseline is made of the project's WBS, WBS Dictionary, and the Project Scope Statement. The activity list provides for estimating, scheduling, executing, and monitoring and controlling the project work. The scope baseline is an element of the project management plan. The contents of the scope baseline include the following: Project scope statement: It includes the product scope description and the project deliverables, and defines the product user acceptance criteria. WBS: It defines each deliverable and the decomposition of the deliverables into work packages. WBS
dictionary: It contains the detailed description of work and technical documentation for each
WBS element. Answer option D is incorrect. Estimates do provide a basis for creating time and cost estimates. Answer option B is incorrect. Activities are executed in the project. Answer option C is incorrect. Activities are scheduled as part of project planning.
QUESTION: 319
Tom is the project manager of the GHQ Project for his organization and he is working on recovering the project schedule. As Tom examines his schedule, he is especially aware of project activities with hard logic. What is hard logic?
1. Hard logic describes activities that can be completed in any order but are positioned with finish-to-start relationships.
2. Hard logic describes activities that have external constraints, such as a vendor.
3. Hard logic describes activities that must be completed in a particular order unless additional resources with comparable skill sets can be added to the project.
4. Hard logic describes activities that must be completed in a particular order.
Answer: D
Explanation:
Hard logic, also known as mandatory dependencies, describes activities that must be completed in a particular order. Hard logic is a binding connection between activities. It is also known as mandatory dependency or hard dependency. Hard logic requires activities to take place in a specific order according to the nature of work. It is a well-built connection where an activity cannot start until and unless a previous one is completed. There are also substantial hard logic connections where soft logic does not usually apply. Several activities rely on hard logic for the successful completion of the project. Answer options B, A, and C are incorrect. These are not a valid description of hard logic.
QUESTION: 320
You are the project manager for your organization. You are working with your project team to create the schedule baseline for your project. You will also be creating the schedule data for this project. The schedule data typically includes all of the following except for which one?
1. Risk activities
2. Schedule activities
3. Activity attributes
4. Schedule milestones
Answer: A
Explanation:
Risk activities are not part of the schedule data. Risk is documented in the risk register, and monitored and controlled throughout the project. In some instances, risk may be part of the activity attributes. The schedule data includes the schedule milestones, schedule activities, activity attributes, and the assumptions and constraints. The schedule data includes the schedule activities, schedule milestones, activity attributes, and documentation of all known assumptions and constraints. The sum of additional data varies by application area. The schedule data commonly supplied as supporting details includes: Resource requirement by time period, frequently in the category of histogram Alternative schedules, such as best case or worst case, or resource leveled, with or without imposed dates Scheduling of contingency reserves Answer option D is incorrect. Schedule milestones are part of the schedule data. A Answer option B is incorrect. Schedule activities are part of the schedule data. Answer option
C is incorrect. Activity attributes are part of the schedule data.
QUESTION: 321
Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member,
reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:
If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?
1. The project will complete on time.
2. The project will be late by one day.
3. The project will be late by two days.
4. The project will be early by two days.
Answer: Pending. Please send your suggestions to support@
QUESTION: 322
Which of the following provides a method to track project progress during project execution against what was planned?
1. Team members profile
2. Benefit-cost ratio
3. Schedule baseline
4. Detailed project budget
Answer: C
Explanation:
A schedule baseline provides a method to track project progress during project execution against what was planned.
What is schedule baseline?
Schedule baseline is a project schedule used in measuring project progress. It helps provide a comparison with the real progress of work against the schedule and to determine if performance to date is within acceptable parameters. Any change caused by change in scope of the project invalidates the original schedule and requires a new baseline schedule. Answer
options D, A, and B are incorrect. A detailed project budget, team members profile, and benefit- cost ratio will not help you track project progress.
What is BCR?
A benefit-cost ratio (BCR) is an indicator, used in the formal discipline of cost-benefit analysis, that attempts to summarize the overall value for money of a project or proposal. A BCR is the ratio of the benefits of a project or proposal, expressed in monetary terms, relative to its costs, also expressed in monetary terms. All benefits and costs should be expressed in discounted present values. For e.g., a BCR of $3.8 indicates a payback of $3.8 for each dollar expended.
QUESTION: 323
You have been hired as a contract project manager for Tech Perfect Inc. The project has already been started. Sufficient details of the project have already been structured. You are working with your team for cost estimation of the project. Which of the following estimating techniques will you use for the highest degree of accuracy?
1. Parametric modeling
2. Analogous
3. Top-down
4. Bottom-up
Answer: D
Explanation:
According to the question, you have to use the estimating technique that has a higher degree of
accuracy. The most accurate estimating technique is bottom-up estimating. What is bottom-up estimating?
Bottom-up is a cost estimating technique that involves estimating the cost of individual work
packages or schedule activities with the lowest level of detail. The detailed cost is rolled up (or summarized) to higher levels for total project estimates. This summarized data is very useful for reporting and tracking purposes. Bottom-up estimating provides a higher degree of accuracy, provided the estimates at the work package level are accurate. Answer options C, A, and B are incorrect. Parametric modeling and analogous estimating techniques use top-down estimation model. These are less accurate than the bottom-up estimation.
What is analogous estimating?
Analogous is an estimating technique that uses the values of parameter, such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous, similar activity as the basis for estimation of the same parameter for a future activity. It is a top- down estimating technique and is a form of expert judgment. It provides a lower degree of accuracy than other estimating techniques. This technique is primarily used when there is a limited amount of detailed information about the project or program.
What is parametric modeling?
Parametric modeling is an estimating technique that uses parameters, or project characteristics, to forecast project costs. It involves a top-down approach and is similar but more accurate than analogous estimating. It uses historical data and other variables to calculate an estimate for activity parameters, such as scope, cost, budget, and duration.
QUESTION: 324
Beth is the project manager of the KJH project. Sarah is Beth's administrative assistant and Ben is the project team leader. Beth's project has eight virtual teams throughout the world that will be working on the activities relevant to the deliverables in their locales. Thomas, the project sponsor, has told Beth that he is to be kept abreast of all communication between her project and the stakeholders. In this project, who is the lead person responsible for communication with all stakeholders?
1. Thomas
2. Sarah
3. Each of the team leaders for the eight virtual teams
4. Beth
Answer: D
Explanation:
Beth, the project manager, is responsible for communication with all stakeholders. According to the PMBOK, the project manager occupies the center of the interactions between stakeholders
and the project itself. Answer option B is incorrect. Sarah may help with the communications,
but she is not responsible for the communications. Answer option A is incorrect. Thomas, the project sponsor, just needs to be kept abreast of the information. Answer option C is incorrect. The project team leaders for the virtual sites are not responsible for communicating with the project stakeholders.
QUESTION: 325
What project management plan will document the time frame and frequency for the distribution of required information?
1. Scope Management Plan
2. Communications Management Plan
3. Stakeholder Management Plan
4. Schedule Management Plan
Answer: B
Explanation:
The project's Communications Management Plan defines what information will be distributed, when it will be distributed, to whom it will be distributed, and the modality of the information. Answer option D is incorrect. The Schedule Management Plan defines the project work, when the project work will happen, resource utilization, and how the schedule will be monitored and controlled. Answer option C is incorrect. There is a stakeholder management strategy, but not a Stakeholder Management Plan. Answer option A is incorrect. The project's Scope Management Plan defines how the scope will be created, how the changes will be allowed, how the scope will be executed, monitored and controlled, and finally closed.
QUESTION: 326
Fill in the blank with the appropriate word. When activities are logically linked, they become the .
Answer: Schedule.
Explanation:
An activity is an individual element of work that is logically linked to other activities to form the schedule. Its primary characteristics include an overall duration based upon the resources applied to it (manpower, material, and equipment), as well as a start and completion date that is tied to a work calendar. It also has a relationship with other activities (predecessors and successors).
QUESTION: 327
Examine the figure given below.
In this project network diagram, what is the total float for Activity I?
1. Three
2. Zero
3. Five
4. One
Answer: A
Explanation:
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for Activity I is Day 20. Therefore, the difference of the early start and the late start reveals the float as three days. It is possible, and acceptable, to use the difference of the early finish and the late finish to find the float, as the value will be the same amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total float.

Killexams has introduced Online Test Engine (OTE) that supports iPhone, iPad, Android, Windows and Mac. PMI-SP Online Testing system will helps you to study and practice using any device. Our OTE provide all features to help you memorize and practice questions Dumps while you are travelling or visiting somewhere. It is best to Practice PMI-SP exam Questions so that you can answer all the questions asked in test center. Our Test Engine uses Questions and Answers from real PMI Scheduling Professional exam.

Killexams Online Test Engine Test Screen   Killexams Online Test Engine Progress Chart   Killexams Online Test Engine Test History Graph   Killexams Online Test Engine Settings   Killexams Online Test Engine Performance History   Killexams Online Test Engine Result Details


Online Test Engine maintains performance records, performance graphs, explanations and references (if provided). Automated test preparation makes much easy to cover complete pool of questions in fastest way possible. PMI-SP Test Engine is updated on daily basis.

Free PMI-SP TestPrep with Free PDF and Free PDF

Studying PMI-SP course books alone isn't enough to pass the PMI-SP exam, as there are many tricky questions that can lead to failure. At killexams.com, we've taken care of these situations by collecting PMI-SP Exam Cram. We regularly update our PMI-SP Exam Questions to make it easy for candidates to get and memorize before attempting the real PMI-SP exam.

Latest 2025 Updated PMI-SP Real exam Questions

To achieve success in the PMI PMI-SP exam, one needs to have a clear understanding of the course description, syllabus, and objectives. Merely studying the PMI-SP course guide is not enough. To be fully prepared, you must familiarize yourself with difficult scenarios and questions that may appear on the real PMI-SP exam. You can visit killexams.com to get free PMI-SP PDF trial questions and gain confidence in our PMI Scheduling Professional questions. Once satisfied, you can register to get the complete version of PMI-SP Exam Questions at an attractive discount. Installing PMI-SP VCE exam simulator on your computer, memorizing PMI-SP Study Guide, and taking practice exams regularly with VCE exam simulator will prepare you for the real PMI-SP exam. Once you feel ready, you can proceed to the Test Center and register for the real exam. If you urgently need to pass the PMI PMI-SP exam to find a job or Improve your current position, you can rely on killexams.com. We have a team of professionals who collect PMI-SP real exam questions to ensure that you pass the PMI Scheduling Professional exam. You can get the latest PMI-SP exam questions every time you log into your account. While there are many institutions that offer PMI-SP Practice Test, valid and up-to-date [YEAR] PMI-SP Exam Questions are hard to come by. Be wary of free dumps provided on the web, as you may end up failing the exam. Instead, paying a small fee for killexams PMI-SP braindump questions is a better investment than risking a large exam fee. Passing the PMI Scheduling Professional exam is easy if you have a clear understanding of the PMI-SP syllabus and access to the latest question bank. It is recommended to read and practice braindump questions to ensure quick success. You must learn about the tricky questions asked in the real PMI-SP exam. To help you prepare, killexams.com offers free PMI-SP Cram Guide trial questions. Once confident, you can register to get Exam Questions of PMI-SP Study Guide. Installing the VCE exam simulator on your PC, memorizing PMI-SP Study Guide, and taking practice exams regularly will further enhance your chances of passing the real PMI-SP exam. When you feel confident that you have memorized all the questions in the PMI Scheduling Professional question bank, proceed to the Test Center and enroll for the real exam.

Tags

PMI-SP Practice Questions, PMI-SP study guides, PMI-SP Questions and Answers, PMI-SP Free PDF, PMI-SP TestPrep, Pass4sure PMI-SP, PMI-SP Practice Test, get PMI-SP Practice Questions, Free PMI-SP pdf, PMI-SP Question Bank, PMI-SP Real Questions, PMI-SP Mock Test, PMI-SP Bootcamp, PMI-SP Download, PMI-SP VCE, PMI-SP Test Engine

Killexams Review | Reputation | Testimonials | Customer Feedback




With two weeks left for my PMI-SP exam, I felt helpless due to my wrong practices. I needed to pass the exam to change my job, but my worries were eliminated when I discovered the Dumps provided by killexams.com. The rich and unique content of the guide, along with the easy and brief answers, helped me understand the Topics with ease. The PMI-SP official Cert guide also came in handy.
Lee [2025-6-19]


I am not a first-time user of Killexams for my PMI-SP exam. I have used their materials for some vendor exams before and have not failed once. I rely on their guidance. This time around, I encountered technical problems with my computer and had to contact their customer support to double-check something. They were top-notch and helped me sort things out, even though the problem was on my end and not their software program.
Richard [2025-5-7]


Thanks to the braindump provided by killexams.com, I passed the PMI-SP exam with ease. The material was 99% valid and included all the latest updates. I only got two queries wrong, and I am thrilled and relieved to have passed the exam. Killexams.com exam Simulator and Dumps material proved to be the perfect combination to prepare for the exam.
Richard [2025-6-14]

More PMI-SP testimonials...

PMI-SP Exam

User: Nastasya*****

I am glad that I discovered Killexams.com online and even happier that I bought the PMI-SP package before my exam. I did not have much time to spare, and the package gave me the preparation I needed. The PMI-SP exam simulator is appropriate, and it covers the areas and questions they test during the PMI-SP exam. While one may find nearly anything online for free, this product is worth every penny. I am satisfied with the guidance process and even more so with the result - I passed PMI-SP with flying colors.
User: Nikolaj*****

Using killexams.com practice tests, I managed to pass the PMI-SP exam with ease. I am grateful for their support and detailed guidance, which was virtually supportive throughout the entire process. I highly recommend killexams.com for anyone seeking high-quality resources for certification exams.
User: Zvezda*****

After failing the pmi-sp exam for the first time, I felt like I was on my own. I searched the web for test help and found many websites offering practice exams for around $200. Killexams.com was the lowest-priced option, and even though I could not afford it, I decided to provide it a shot. To my surprise, I passed my certification exam with a 98%! Killexams.com provided nearly every question on the exam, making them stand out in my book. I would gladly offer a testimonial for this successful resource.
User: Neia*****

I am thrilled to say that I passed the pmi-sp exam with an 80% score thanks to Killexams.com. I was skeptical at first, but their cram proved to be the perfect solution for me. I highly recommend their service to anyone looking to pass their certification exams.
User: Bernardo*****

Investing in Killexams.com was worth it. The practice exams are noteworthy and provide good value for the money. The Dumps are valid and accurate, and I even double-tested them with friends. Passing the exam was easy, and I wholeheartedly recommend Killexams.com to anyone looking to take the pmi-sp exam.

PMI-SP Exam

Question: How much time I need to spend on PMI-SP test prep?
Answer: It is up to you. You can pass your exam within the shortest possible time. If you are free and you have more time to study, you can prepare for an exam even in 24 hours. But we recommend taking your time to study and practice PMI-SP practice questions until you are sure that you can answer all the questions that will be asked in the real PMI-SP exam. Visit killexams.com and register to get the complete question bank of PMI-SP exam test prep. These PMI-SP exam questions are taken from real exam sources, that's why these PMI-SP exam questions are sufficient to read and pass the exam. Although you can use other sources also for improvement of knowledge like textbooks and other aid material these PMI-SP questions are sufficient to pass the exam.
Question: I do not remember any of my login information, what should I do?
Answer: You can reset your account password anytime if you forgot. You can go to the login page and click on forgot password. Enter your email address and the system will reset your password to some random password and send it in your email box. You can click https://killexams.com/forgot-username-password to recover your password. If you forgot your email address also, you need to contact support and ask to search your login details with your full name, etc.
Question: How can I contact killexams technical Support?
Answer: You can contact technical support via live chat or email to support. Our technical support team handles all exam-related queries.
Question: Where am I able to find out PMI-SP real exam questions?
Answer: Yes. You will be able to get up-to-date real Dumps to the PMI-SP exam. If there will be any update in the exam, it will be automatically copied in your get section and you will receive an intimation email. You can memorize and practice these Dumps with the VCE exam simulator. It will train you enough to get good marks in the exam.
Question: Do you want latest real PMI-SP test questions to read?
Answer: This is the right place to get the latest and 100% valid real PMI-SP exam questions with VCE practice tests. You just need to memorize and practice these questions and reset ensured. You will pass the exam with good marks.

Frequently Asked Questions about Killexams Practice Tests


Can I pass the PMI-SP exam in one week?
One week is more than sufficient if you daily practice with killexams PMI-SP practice questions and spare more time to study. These Dumps are very easy to memorize and practice. The more you practice, the more you feel confident about the real test.



I need latest syllabus of PMI-SP exam to pass, where should I go?
If you want the latest PMI-SP syllabus, Killexams.com is the right place to get the latest and up-to-date PMI-SP practice questions that work great in the real PMI-SP test. These PMI-SP questions are carefully collected and included in PMI-SP question bank. You can register at killexams and get the complete question bank. Practice with PMI-SP exam simulator and get Good Score in the exam.

Is PMI-SP exam test engine software free?
Killexams do not charge for exam Simulator Software, but you have to buy the exam files. Software is provided free of cost on the website. You can get and install any time. When you buy PMI-SP exam, you will be able to get PMI-SP.sis files that are exam files. You can use this exam simulator software with all the exams you buy from killexams.

Is Killexams.com Legit?

Certainly, Killexams is 100% legit together with fully well-performing. There are several functions that makes killexams.com traditional and reliable. It provides up to date and fully valid cheatsheet including real exams questions and answers. Price is very low as compared to almost all services on internet. The Dumps are up graded on regular basis along with most latest brain dumps. Killexams account arrangement and device delivery is amazingly fast. Data downloading is normally unlimited and extremely fast. Help is available via Livechat and Electronic mail. These are the characteristics that makes killexams.com a sturdy website that supply cheatsheet with real exams questions.

Other Sources


PMI-SP - PMI Scheduling Professional teaching
PMI-SP - PMI Scheduling Professional Study Guide
PMI-SP - PMI Scheduling Professional Dumps
PMI-SP - PMI Scheduling Professional Free exam PDF
PMI-SP - PMI Scheduling Professional PDF Braindumps
PMI-SP - PMI Scheduling Professional exam syllabus
PMI-SP - PMI Scheduling Professional test
PMI-SP - PMI Scheduling Professional test prep
PMI-SP - PMI Scheduling Professional book
PMI-SP - PMI Scheduling Professional dumps
PMI-SP - PMI Scheduling Professional Free exam PDF
PMI-SP - PMI Scheduling Professional Test Prep
PMI-SP - PMI Scheduling Professional information source
PMI-SP - PMI Scheduling Professional real Questions
PMI-SP - PMI Scheduling Professional exam Braindumps
PMI-SP - PMI Scheduling Professional exam dumps
PMI-SP - PMI Scheduling Professional syllabus
PMI-SP - PMI Scheduling Professional Cheatsheet
PMI-SP - PMI Scheduling Professional study help
PMI-SP - PMI Scheduling Professional teaching
PMI-SP - PMI Scheduling Professional Practice Questions
PMI-SP - PMI Scheduling Professional boot camp
PMI-SP - PMI Scheduling Professional information source
PMI-SP - PMI Scheduling Professional answers
PMI-SP - PMI Scheduling Professional guide
PMI-SP - PMI Scheduling Professional braindumps
PMI-SP - PMI Scheduling Professional Questions and Answers
PMI-SP - PMI Scheduling Professional braindumps
PMI-SP - PMI Scheduling Professional braindumps
PMI-SP - PMI Scheduling Professional exam contents
PMI-SP - PMI Scheduling Professional Cheatsheet
PMI-SP - PMI Scheduling Professional exam dumps
PMI-SP - PMI Scheduling Professional exam format
PMI-SP - PMI Scheduling Professional study help
PMI-SP - PMI Scheduling Professional braindumps
PMI-SP - PMI Scheduling Professional outline
PMI-SP - PMI Scheduling Professional test
PMI-SP - PMI Scheduling Professional PDF Braindumps
PMI-SP - PMI Scheduling Professional PDF Questions
PMI-SP - PMI Scheduling Professional exam contents
PMI-SP - PMI Scheduling Professional study tips
PMI-SP - PMI Scheduling Professional Questions and Answers
PMI-SP - PMI Scheduling Professional guide
PMI-SP - PMI Scheduling Professional exam success

Which is the best testprep site of 2025?

There are several Dumps provider in the market claiming that they provide Real exam Questions, Braindumps, Practice Tests, Study Guides, cheat sheet and many other names, but most of them are re-sellers that do not update their contents frequently. Killexams.com is best website of Year 2025 that understands the issue candidates face when they spend their time studying obsolete contents taken from free pdf get sites or reseller sites. That is why killexams update exam Dumps with the same frequency as they are updated in Real Test. Testprep provided by killexams.com are Reliable, Up-to-date and validated by Certified Professionals. They maintain question bank of valid Questions that is kept up-to-date by checking update on daily basis.

If you want to Pass your exam Fast with improvement in your knowledge about latest course contents and topics, We recommend to get PDF exam Questions from killexams.com and get ready for real exam. When you feel that you should register for Premium Version, Just choose visit killexams.com and register, you will receive your Username/Password in your Email within 5 to 10 minutes. All the future updates and changes in Dumps will be provided in your get Account. You can get Premium exam questions files as many times as you want, There is no limit.

Killexams.com has provided VCE practice questions Software to Practice your exam by Taking Test Frequently. It asks the Real exam Questions and Marks Your Progress. You can take test as many times as you want. There is no limit. It will make your test prep very fast and effective. When you start getting 100% Marks with complete Pool of Questions, you will be ready to take real Test. Go register for Test in Test Center and Enjoy your Success.

Free PMI-SP Practice Test Download
Home